Apollo 17 Mission Plan

The highly successful Apollo 17 manned lunar landing mission was the final in a series of missions in the Apollo Program. Scientific objectives for the mission included geological surveying and sampling of materials and surface features in the area of the Taurus-Littrow region; deploying and activating surface experiments; and conducting inflight experiments and photographic tasks during lunar orbit and trans-Earth coast.

Mission Event List and Timeline

EVENT       DATE & TIME (EST)       MISSION TIME
Launch       December 7   12:33:00 am 00:00:00
Translunar injection       03:45:37 am 03:12:37
CSM-LM docking       04:39:45 am 03:56:45
Lunar orbit insertion       December 10   02:47:23 pm 86:14:23
CSM-LM separation       December 11   12:20:56 pm 107:47:56
Lunar landing       02:54:57 pm 110:21:57
First EVA       06:54:49 pm 114:21:49
Second EVA       December 12   06:28:06 pm 137:55:06
Third EVA       December 13   05:25:48 pm 160:52:48
Lunar liftoff       December 14   05:54:37 pm 185:21:37
LM-CSM docking       08:10:15 pm 187:37:15
Trans-Earth injection       December 16   06:35:09 pm 234:02:0
Splashdown       December 19   02:24:59 pm 301:51:5